Description of performed works:
Production, delivery and supervision of the installation of switchboard type SIVACON S8
After successful cooperation on the construction of the Kronospan factory in Lapovo and the fulfillment of impossible deadlines, the investor Kronospan sees Montprojekt as a reliable partner and awards us a contract for the delivery of 0.4kV switchboards for their new factory in Ufa, Russia.
14 SIVACON S8 switchboards were delivered in six substations for different production processes – a total of 127 panels of different configurations, supply and bus coupler panels equipped with withdrawable air circuit breakers type 3WL Siemens, power factor correction panels, outgoing panels equipped with a new series of Siemens switch disconnectors with fuses type 3NJ63 that meet all industry standards for reliable distribution of electricity.